Fast Facts...
Square Footage | 187,343 |
Capacity | 1410 |
Board of Trustees - Bond Sale Approval Date | January 29, 2008 |
Contractor | United Construction Company |
Board of Trustees - Contract Approval Date | April 1, 2008 |
Notice to Proceed Date (Date construction commenced) | April 9, 2008 |
Contract Completion Date (approximate at this date) | August 12, 2009 |
Construction Contract Bid Amount | $37,649,394 |
Total Project Cost at Completion (estimated) | $49,000,000 |