Washoe Country School District

May 23, 2012

Change Font Size


New School Construction

New Construction funded by the 2002 Rollover Bond:

 

Project Completion Date
Total Estimated
Project Cost @ Completion
Incline Elementary School Addition
September 3, 2009 $7,000,000
Kendyl Depoali Middle School August 12, 2009 $49,000,000
Spanish Springs High School Addition
August 19, 2006 $8,565,000
North Valleys High School Addition
August 15, 2006 $8,275,000
July 14, 2006 $16,650,000
Miguel Sepulveda Elementary School
May 25, 2006 $15,800,000
Cold Springs Middle School
July 20, 2006 $31,500,000
Yvonne Shaw Middle School
June 30, 2004 $23,103,000
TOTAL:
  $159,893,000